bus in BRT lane pulling into station

Metro Rapid Route A

The City of Madison is building a Bus Rapid Transit (BRT) system as part of an effort to provide better access to jobs, reduce travel times, and improve transit equity throughout the region.

The BRT system will start with an east-west line from Junction Rd. to East Towne through the downtown and campus area.

Construction of dedicated bus lanes, passenger stations, and implementation of larger all-electric articulated buses will last into next year. The system is expected to go officially online at the end of 2024.

What is BRT? / Why does Madison need BRT?  


BRT map

View Larger Map


Plans/Documents


Construction Updates

Updated October 2023

Crews are building the stations and other infrastructure along the line.
 

Station

Summary

Status

Junction

New BRT and local bus terminal off street

Under construction (buses are currently stopping at Junction and Watts)

High Point

Center running station on the east side

Platform complete, shelter underway

Westfield

Center running station on the east side

Platform complete, awaiting shelter

Grand Canyon

Center running station on the east side

Platform complete, awaiting shelter

Island

Center running station on the west side

Platform complete, awaiting shelter

Rosa

Center running station on the west side

Platform complete, awaiting shelter

Whitney - Mineral Point

Center running station on the west side

Not started

Regent

Center running station on the south side

Platform complete, awaiting shelter

Eau Claire

Center running station on the east side

Platform complete, shelter underway

Segoe

Northbound center running station, southbound side running station on Segoe

Not started

Midvale

Center running station on the west side

Under construction

Shorewood

Center running station on the east side, westbound left turns will no longer be allowed

Not started

University Bay

Center running station on the east side

Not started

Orchard

Side running stations on University and Johnson

Not started

East Campus

Two side running platforms on University and one on Johnson

Platforms complete, awaiting shelter

State Street

Westbound side running station at Gorham, Eastbound side running station at Johnson

Not started

Capitol Square

Westbound side running station on Mifflin, Eastbound side running station on Main

Not started

Blair

Center running station on the west side

Under construction

Paterson

Center running station on the west side, eastbound left turns will no longer be allowed

Under construction

Baldwin

Center running station on the west side, eastbound left turns will no longer be allowed

Under construction

First Street

Center running station on the west side

Under construction

Fourth Street

Center running station on the east side, westbound left turns will no longer be allowed

Under construction

Milwaukee - North

Westbound center running station on the west side, eastbound center running station on the east side

Not started

Marquette

Center running station on the west side

Under construction

Melvin - Rethke

Center running station on the west side, eastbound left turns will no longer be allowed

Under construction

Wright - Fair Oaks

Center running station on the west side

Not started

Anderson

Side running stations on the east side

Platforms complete, awaiting shelter

Mendota

Side running stations

Eastbound under construction

Thierer - Portage

Side running stations

Eastbound under construction

Independence

Side running stations

Eastbound under construction

East Springs

Side running stations

Eastbound under construction


Past Public Meetings

Watch recordings and review materials from past meetings to learn more about the construction process. 

Mineral Point Sidewalk Widening

East Side (Blair Street to East Towne)

West Side (Junction Rd. to University Bay Dr.)

Central (University Bay Dr. to Blair St.)

Mineral Point Sidewalk Widening


Construction Contact Information

brtconstruction@cityofmadison.com

(608) 622-9659 ​​


Stay Informed on Madison's BRT Project

For new meeting updates and the latest information on Madison's Bus Rapid Transit System: