Last Updated: 06/28/2019

Construction Update

Street signs need to be installed then road can be open to all traffic.

Reetz Rd (Freeport – Hammersley) is open to local traffic only.

Project Description

The project consists of resurfacing with new asphalt pavement, and spot replacement of concrete curb and gutter, drive aprons, and sidewalk. Utility replacement will include new storm sewer improvements.

Project Limits

Reetz Road – Raymond Road to Hammersley Road

Altem Circle – Reetz Road to west end

Project Schedule

City Work will begin in late April to Early May and is expect to last for 2-3 months.