Last Updated: 03/26/2019

Project Update

Project Complete

Bike route is maintained on Mifflin.

Project Description

This project will remove and replace concrete curb and gutter; remove and replace sidewalk, as needed; remove and replace drive aprons, install a new asphalt pavement; replace sanitary sewer main and laterals; replace the water main; replace or extend storm sewer, as necessary. During construction, local access will be maintained from at least one end of Hancock Street. Residents will be provided with at least 48 hours' notice if changes to access are proposed.

Project Limits

E Washington Avenue to E Johnson Street

Project Schedule

July 27, 2017 - Public Information Meeting
August 23, 2017 - Board of Public Works
September 5, 2017 - Common Council
April 2, 2018 - Begin Construction

Public Information Meeting

A Public Information Meeting was held on July 27, 2017. The plan from this meeting can be found here: PIM Display