Last Updated: 09/18/2023

Project Update

9/18/2023 Update: 
Phase 1 Update

The Contractor is planning to pave Hammersley Rd from Brookwood Rd/Rae Ln to Whitney Way on Tuesday, September 19th, including the new off-street path and the roadway. Final paving work may continue into the end of the week. After the paving rollers have gone over the new asphalt surface, the pavement is rideable within 3 hours. Pavement markings and terrace restoration will follow in the coming weeks, as well as final traffic signage along the entire project limits.

Phase 2 Update

The design for Phase 2 of Hammersley Rd (Gilbert Rd to the W Beltline Frontage Rd) is currently underway after the proposed design was approved in Fall 2022. The project is scheduled to be bid this Fall/Winter with construction on Phase 2 beginning in Spring 2024 and going until Fall 2024. Construction notification will be mailed out to impacted residents within Phase 2 ahead of the start of construction.

Project Overview
The proposed resurfacing of Hammersley Rd includes the replacement of asphalt pavement, sanitary sewer main & laterals, storm sewer, and water main. In addition, the City is proposing to redesign Hammersley Rd (2023: Brookwood to Gilbert & 2024: Gilbert to Beltline) to a 24-ft wide street with 2-way traffic, removing all existing on-street parking and on-street bike lanes, and constructing an 8-10’ off-street, multi-use path (for bikes & pedestrians) on the north-side of Hammersley Rd with curb & gutter and grass terrace (of varying-width) between the path and the street (see latest proposed plan). The cost to construct the multi-use path would not be assessed to adjacent property owners and the City would be responsible for maintaining the path, including snow removal. Property owners would responsible for mowing the grass terrace between the proposed path and the street. To accommodate some on-street parking on the longest block of Hammersley between Brookwood Rd and Whitney Way, an on-street parking pocket is proposed mid-block in front of 5909 and 5905 Hammersley that would accommodate 2-3 on-street parking spots.To provide a safe path crossing at Whitney Way, City Staff is proposing to remove the left-turn from Eastbound Hammersley Rd onto Northbound Whitney Way to allow for combining the northerly-side median islands into one larger median refuge for bikes & pedestrians. Removing the left turn shortens and straightens the path crossing, reduces potential conflict points, and in conjunction with a tall, overhead Rectangular Rapid Flashing Beacon (RRFB) provides the best possible path crossing considering the large hill to the south on Whitney Way. This design is consistent with City Policies, such as Vision Zero and Complete Streets, that prioritizes safety of all modes of transportation for all ages and abilities. Note that the left-turn from Northbound Whitney Way to Westbound Hammersley Rd would be maintained.

The proposed design on the north-side of Hammersley Rd between Brookwood Rd and Whitney Way includes an 8-8.5-ft wide asphalt path, which was narrowed slightly from previous proposals (9-ft) in order to provide a 3-ft grass terrace and stay within the existing street footprint to avoid substantial tree/grading impacts. A portion of the path over this stretch will be 8-ft wide as to not impact tree roots directly behind the existing curb. A 3-ft grass terrace provides space for relocated mailboxes, trash bins, and leaf/yard waste pick-up. The proposed design on the north-side of Hammersley Rd from Whitney Way to the Beltline Frontage Rd includes a 10-ft wide asphalt path and a 5-ft wide grass terrace.

With the proposed removal of the on-street parking lane, mail and other deliveries would continue on Hammersley Rd, although the delivery methods may change. Delivery trucks would either turn into individual driveways or temporarily block the travel lane, both of which are common scenarios throughout the City where there is no parking space available. Home Contractors will most likely need to park in individual driveways when visiting specific residences, which is also typical throughout the city.

Backyard Sanitary Sewer 
After investigation of the backyard sanitary sewer system currently serving select lots on Hammersley Rd (5718, 5714, 5710 and 5706 Hammersley Rd), the City has determined that removing that main from service and instead serving those lots from Hammersley would be impractical. Therefore, the backyard service will remain in place. Please note, if you are one of the affected lots, that this should not negatively impact your sanitary sewer service; the City will continue to maintain this service and, if necessarily, will pursue an in-situ lining rehabilitation. No further survey will be required at these lots.

Assessments

There will be assessments for both phases of construction on Hammersley Rd for the resurfacing portions of the work. There will be NO assessments for work related to the installation of the off-street, shared-use path – including curb & gutter and driveway work necessary to construct the path. The assessments to fronting property owners on Hammersley Rd will consist of 50% of the cost to remove & replace concrete driveways, asphalt driveways, concrete sidewalk, and concrete curb & gutter either due to poor condition (as determined by the Construction Inspection staff) OR as needed to replace the sanitary sewer lateral to the property line. Fronting property owners will also be assessed for 50% of the cost to install new concrete sidewalk. In addition, 25% of the cost to replace and reconnect the sanitary sewer lateral from the sewer main to the property line will be assessed to property owners with replaced laterals, and 100% of the cost for private storm sewer connections will be assessed if requested by the property owner.

Want to hear from the project manager? Listen to our 16-minute discussion with Engineer and Project Manager Aaron Canton in our Everyday Engineering Podcast Episode: Orange Barrels: Hammersley Road: 
 

Project Limits

Hammersley Road Resurfacing 2023 Project: Brookwood Road to Gilbert Road

Hammersley Road Resurfacing 2024 Project: Gilbert Rd to W Beltline Frontage Road

Hammersely Map

Project Schedule

Hammersley Road Resurfacing: Phase 1 (Brookwood Rd to Gilbert Rd)

Hammersley Road Resurfacing: Phase 2 (Gilbert Rd to W Beltline Frontage Rd)

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

City Process Meetings

Hammersley Road Resurfacing: Phase 1 (Brookwood Rd to Gilbert Rd)

Transportation Commission: 01/12/2022 (Review & Feedback)

Transportation Commission: 02/23/2022 (Review & Feedback)

Transportation Commission: 03/09/20222 (Final Approval)

Board of Public Works: 04/06/2022

Common Council: 04/19/2022

Hammersley Road Resurfacing: Phase 2 (Gilbert Rd to W Beltline Frontage Rd)

Transportation Commission: 09/14/2022

Board of Public Works: 10/12/2022

Common Council: 10/25/2022

Mailings

Phase 1 Board of Public Works Public Hearing Notice: Cover Letter, Fact Sheet, Notice, Assessments
Phase 1 Common Council Public Hearing Notice: Notice
Phase 1 Adopted Resolution: Cover LetterFinance Letter, Resolution, Assessments
Phase 2 Board of Public Works Public Hearing Notice: Cover Letter, Fact Sheet, Notice, Assessments
Phase 2 Common Council Pubic Hearing Notice: Notice
Phase 2 Adopted Resolution: Cover Letter, Finance Letter, Resolution, Assessments
Phase 1 Start of Construction: Cover Letter, Fact Sheet