Archived News: This news release is more than one year old and may include outdated information.

The contractor on the CTH M project will close the CTH M / CTH PD intersection starting Friday, June 7, 2019 at 8:00 p.m. to complete asphalt paving operations within the intersection as well as utility crossings that cross both CTH M and CTH PD. The intersection will be re-opened on Sunday, June 9, 2019 at 6:00 a.m., pending any unforeseen conditions. The approximate hard roadway closures will be placed at the following:

  • CTH M, south leg: Hard barricade closure will be placed approximately just north of the north Stony Ridge Circle access point. Staggered barricades will be placed near Cross Country Road to allow access for residents.
  • CTH M, north leg: Hard barricade closure will be placed approximately just south of Flagstone Drive. Staggered barricades will be placed at Mid Town Road to allow access for residents.
  • CTH PD, east leg: Hard barricade closure will be placed approximately near Meriter Way. Staggered barricades will be placed near High Point Road to allow access for residents.
  • CTH PD, west leg: Hard barricade closure will be placed approximately just east of the UW Ridge Golf Course driveway. Staggered barricades will be placed near Woods Road to allow access for residents and the UW Ridge Golf course. 

During the closure, portable message boards will be placed throughout the area (including on CTH M, CTH PD, HWY 12 / 14, and HWY 18 / 151) to notify motorist of the closure. The use of alternate routes will be required during the closure timeframe.

Please see attached map of the closure area.

Direct any questions to the contact person listed.
 