Last Updated: 02/28/2023

Latest Update

3/21/2022 Update:
Thank you everyone for attending the March 21, 2022 Public Information Meeting. The March 21, 2022 Public Information Meeting Recording is now available. 

March 21, 2022 Public Information Meeting PowerPoint Presentation

Plans and Specifications and authorizing the Board of Public Works to advertise the project will be presented at the April 6, 2022 Board of Public Works meeting.

Project Overview

This is a street resurfacing project with limit sanitary sewer replacement and storm sewer improvements.
Project Overview Plan
View Proposed Assessments

Project Limits

Tokay Boulevard: South Segoe Road to South Whitney Way

Project Schedule 

Approving Plans Specifications: April 6, 2022
Bid Advertisement: April 28, 2022

Start of Construction: End of July 2022

End of Construction: October 2022

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

City Process, Meetings

Board of Public Works: April 6, 2022

Common Council: April 19, 2022

Mailings

Start Work Letter & Fact Sheet