South Park Street Concrete Pavement Repairs
Project Update
2022 Update:
This project is complete.
Project Overview
This is a concrete pavement replacement project for the southbound lanes only. This is a continuation of the 2019 Concrete pavement replacement project for the northbound lanes of South Park. The contractor will replace transverse, longitudinal joints and concrete pavement that is in poor condition for the southbound lanes of South Park Street.
April 8, 2021 work start letter and fact sheet
Project Limits
South Park Street: West Badger Road to the Railroad Crossing and from West Olin Avenue to West Washington Avenue
Project Schedule
Approving Plans Specifications: Jan.6, 2021
Bid Advertisement: Feb.4, 2021
Start of Construction: May 2021
End of Construction: August 2021
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Documents (Assessments Letters, Work Start Notifications, Fact Sheets)
April 8, 2021 work start letter and fact sheet
Public Information Meetings
Jan. 4, 2021 Public Information Meeting PowerPoint Presentation
Jan. 4, 2021 Public Information Meeting Recording
City Process, Meetings
Board of Public Works: Jan. 6, 2021
Common Council: Jan. 19, 2021