Last Updated: 11/03/2023

Latest Update 

11/3/2023 Update: 

Work the Week of Nov. 6, 2023

  • It is anticipated that traffic will remain in the current configuration until approximately November 17, 2023. View an overview of the Stage 4 traffic configuration. PDF

  • A closure of Hill St. began at 7 AM on November 3, 2023. Hill St. is scheduled to reopen by 7 PM on November 4, 2023. An overview showing access to local businesses and access for pedestrians can be viewed here: Hill Street Closure PDF

  • Concrete curb and sidewalk installation on the south side of University Ave. is anticipated to continue at various locations throughout the project limits. Access to businesses will be maintained during this work; however, please note that available driveway widths may need to be reduced while the concrete is being placed and cured.
  • Installation of new storm sewer, sanitary sewer, and water main will continue between Schmitt Pl. and Farley Ave.
  • Installation of new street lighting fixtures will continue to be installed in areas where curb, sidewalk and asphalt paving have been completed.
  • Please note that short-term traffic flagging, reduced roadway widths and temporary lane shifts may be necessary while underground utilities are being installed at the side streets on the south side of University Ave.

Work the Week of Nov. 13, 2023

  • Concrete curb and sidewalk installation on the south side of University Ave. will be completed during the week.

  • Installation of new storm sewer, sanitary sewer, and water main will be completed between Schmitt Pl. and Farley Ave.

  • The contractor will continue performing roadway grading and placement of aggregates as the underground utilities and services are being completed.
  • Asphalt paving of the eastbound lanes of University Ave. and Farley Ave. is anticipated to be completed during the week.

Traffic/Pedestrian/Bike Impacts

  • Traffic is anticipated to remain in its current configuration until approximately November 17, 2023. Single lane closures and/or traffic flagging operations on University Ave. as well as side streets on the south side of University Ave. may be required during off-peak travel periods (9 AM to 3 PM). Sidewalk and pedestrian crosswalk adjustments, as well as minor changes to Madison Metro Transit bus stop locations, will occur periodically. Please be alert for sidewalk closed and sidewalk detour signage identifying pedestrian routes. Temporary bus stop signage will also be in place identifying any changes to bus stop locations. Note that the work is weather dependent and may be subject to change.
     

View the full University Weekly Update Flyer

Project Overview

University Ave is scheduled for reconstruction from Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave. The City of Madison is jointly participating with the Village of Shorewood Hills on the design and construction. The project includes reconstruction of pavement, curb and gutter, sidewalk as necessary, street lighting, traffic signals, water main, sanitary sewer and storm sewer.  Alternatives to improve pedestrian & bicycle connectivity, bus rapid transit initiatives and stormwater drainage have been reviewed, and the project plans have been updated to include a new pedestrian & bike overpass of University Bay Dr., a widened sidewalk along the southerly side of University Ave., and a 96-inch storm sewer pipe to help improve drainage in the area.  The project continues to be coordinated with the City’s planning efforts for bus rapid transit.

Full Project Map
Typical Section Example
University Bay Overpass Alternative
Project Fact and Details Sheet
Proposed improvments university bay
View a larger image of proposed improvements

 

Project Limits

Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave.

Project Limits Map

Project Schedule

Construction is scheduled for 2022.

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:

Public Information Meetings

City Meetings, Process

Board of Public Works: June 16, 2021

Transportation Commission: April 15, 2020

Common Council: July 6, 2021

Mailings

Extension of work hours for Construction Activities (Starting around Aug. 15, 2022)