Last Updated: 09/17/2021

September 17, 2021 Update: 
The Sycamore Park parking lot is open!

Thank you for your patience as improvements to the lot were completed.


Parking Lot Replacement

Work includes the pavement removal, shaping, paving and pavement marking of the parking stalls for the parking lot.  Also included is the replacement of sections of curbwork at the parking lot islands and some sections of the perimeter curbs that have been damaged by snow removal.


City User Agency: Streets and Parks

Project Status: Construction
1st Advertisement of Bid: May 03, 2021 available only on Bid Express
Bid Due Date: May 20, 2021
Construction Start Date: TBD

Expected Completion Date: October 1, 2021
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
 

August 23 - September 7* The parking lot at Sycamore Park, 4517 Sycamore Ave is scheduled for replacement. The parking lot is adjacent to the off-leash dog park and will be closed during construction. Once construction begins, it is expected to last two weeks.
*Please note that construction and closure dates are weather-dependent and subject to change. 
For more information regarding Dog Off-Leash Parks please click HERE.


Project History

June 18, 2021 File #65576
Awarding Public Works Contract No. 8613, Sycamore Park Parking Lot Repavement.

May 10, 2021 File #65099
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Sycamore Park Parking Lot Replacement