Last Updated: 02/28/2023

Latest Update

1/25/2022 Update:
Thank you to everyone who attended the Jan. 24, 2022 Public Information Meeting. The recording is now available.
Jan. 24, 2022 Public Information Meeting Recording
Jan. 24, 2022 Public Information Meeting PowerPoint Presentation

Plans and Specifications and authorizing the Board of Public Works to advertise the project will be presented at the Feb. 2, 2022 Board of Public Works meeting.

Project Overview

This is a street resurfacing project with sanitary sewer and lateral replacement and storm sewer improvements.
Preliminary Plan

Project Limits

South Owen Drive:  Mineral Point Road to Keating Terrace
Keating Terrace from S. Owen Drive to Caromar Drive
Caromar Drive from Keating Terrace to Tokay Boulevard

Project Schedule

Approving Plans Specifications: Feb. 2, 2022
Bid Advertisement: March 10, 2022
Start of Construction: June 2022
End of Construction: August 2022

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

Jan. 24, 2022 Public Information Meeting Recording
Jan. 24, 2022 Public Information Meeting PowerPoint Presentation

City Meetings, Process

Board of Public Works: Feb. 2, 2022
Common Council: Feb. 22, 2022