Last Updated: 08/01/2023

Latest Update

August 01, 2023
Updated project schedule below.

Project Overview

Installation of a roughly 102 kW solar photovoltaic system at Madison Water Utility Paterson Vehicle Storage Building. The system will consist of roof mounted modules and will produce an estimated 117,300 kWh per year. Once complete 88% of the building’s electricity usage will be generated by the solar array. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.

Project Schedule

City User Agency: City of Madison Water Utility
Design and Planning: Jan – April 2023
1st Advertisement of Bid: N/A
Bid Due Date: N/A
Construction Start Date: October 2023
Expected Completion Date: October 2024

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

City Process Meetings

March 29, 2022 Common Council File #70179
March 02, 2022 Board of Public Works File #70179
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Solar PV - Water Utility Paterson Vehicle Storage