Last Updated: 08/01/2023

Latest Update

August 01, 2023
Project Status: Construction!

Project Overview

Installation of a roughly 25 kW solar photovoltaic system at the John Wall Family Pavilion at Tenney Park. The system will consist of roof mounted modules and will produce an estimated 30,000 kWh per year. Once complete 80% of the building’s electricity usage will be generated by the solar array.  The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.

Project Schedule

City User Agency: City of Madison Engineering
Planning and Design: January – March 2023
1st Advertisement of Bid: N/A
Bid Due Date: N/A
Construction Start Date: August 2023
Expected Completion Date: October 2023