Last Updated: 04/03/2023

Latest Update

April 03, 2023
Project status changed to "Completed".

Project Overview

Replacement of interior lighting including lighting control. This will save energy and maintenance cost.

Project Schedule

City User Agency: Madison Senior Center

1st Advertisement of Bid: February 24, 2022 available only on Bid Express
Pre-Bid Building/Site Contractor Meeting:
      Wednesday, March 02, 2022 @ 9:00 am at the Senior Center located at 330 W. Mifflin St., Madison, WI
Bid Due Date: March 24, 2022
Construction Start Date: May 2022
Expected Completion Date: Dec. 2022

"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

City Process Meetings

Apr. 19, 2022 Common Council File #70732
Apr. 06, 2022 Board of Public Works File#70732
Awarding Public Works Contract No. 9159, Senior Center Lighting Replacement

Jan. 04, 2022 Common Council File #68415
Dec. 15, 2021 Board of Public Works File #68415
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for the Senior Center Lighting Replacement