Last Updated: 03/29/2019

Construction Update

Project is complete

Project Description

This project will remove and replace concrete curb and gutter; remove and replace sidewalk, as needed; remove and replace drive aprons, install a new asphalt pavement; replace sanitary sewer main and laterals; replace the water main; replace storm sewer, as necessary.

Project Limits

N Prospect Ave - Regent St to Van Hise Ave

Project Schedule

March 21 - Board of Public Works
April 10 - Common Council
July 2 - Begin Construction