Last Updated: 02/03/2020

Roof Renovation

This project will provide for the exterior renovation of the cold storage maintenance building. The exterior walls will be extended by 40” to accommodate fork truck traffic and a new roofing system will be installed to allow for removal of existing center columns. The walls will receive masonry treatment and repainted. Overheads will be enlarged and rusted out walk thru door will be replaced. Ventilation will be installed to meet current codes.  The nearby warm storage building will receive repairs to the EFIS stucco walls and the existing metal roof will be re-coated.


Update: April 04, 2018
Project Status:  Construction


City User Agency: Parks Department
1st Advertisement of Bids:  February 02, 2018 available on Bid Express
Bid Due Date: February 22, 2018
Construction Start Date: April 30, 2018
Pre-Bid Building Tour: February 13, 1:30 pm at the project site.
SBE Pre-Bid Meeting: February 16, 2017 1:00 pm at 1600 Emil St., Madison, WI
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."