Lake Mendota Drive
Latest Update
2/25/2022 Update:
Thank you everyone for attending the Feb. 24, 2022 Public Information Meeting. The recording and additional crash information report (as requested) are posted.
- Lake Mendota Drive Survey No. 2 , please complete before March 9 ,2022.
- The City's electronic survey No. 1 results for this project are now available: Lake Mendota Drive Electronic Survey results
- You can now view Lake Mendota Drive Existing Conditions and Property Lines.
- Feb. 24, 2022 Public Information Meeting Recording
- Traffic Engineering Crash Report: Lake Mendota Drive
- Feb. 24, 2022 Public Information Meeting PowerPoint Presentation
- Lake Mendota Dr. Preliminary Plan
Project Overview
The City of Madison is planning to reconstruct Lake Mendota Dr. Due to the size/scope of the work, this work will be completed over several years, with work being completed on several blocks each year. In 2022, work is planned for the western most blocks, in 2023, the eastern blocks, and the middle blocks in 2024.
Lake Mendota Drive Existing Conditions and Property Lines
Lake Mendota Dr. Preliminary Plan
In general, the reconstruction project will include replacement of underground City utilities, especially storm sewer and sanitary sewer, and reconstruction of the street infrastructure (pavement, gravel base) along with any curb or sidewalk installations that are approved for the project(s). We have received many complaints from residents regarding the pavement condition along Lake Mendota Dr., and it has deteriorated to a point where periodic maintenance patching is no longer viable, so the streets will need to be reconstructed to provide a ridable surface for all users.
While there have not been a large number of crashes along Lake Mendota Dr. (6 since 2016), whenever the City proceeds with a significant project, we always review opportunities to improve safety and accessibility. Crash history does help guide our budgeting and project selection process, but, even though this project was scheduled primarily due to the pavement condition and drainage needs, it’s still important to review the project for possible safety improvements. These types of reconstruction projects and investments only occur once every several decades, so it would be irresponsible to ignore known safety and accessibility issues.
We believe that this project can be designed to meet the City’s transportation goals, along with giving strong consideration to the environment. As with all projects, protecting the existing tree canopy is a priority with this project, which is also important for maintaining the character of the neighborhood. With the project, we believe that the street width along Lake Mendota Dr. can be narrowed, so, overall, we hope to not have a significant change in the paved surface area. In terms of salt use, Lake Mendota Dr. is currently a salt route for the streets crews, so a reduction in pavement width would also likely result in a reduction of salt use on the street. Individual properties will have several options for clearing snow/ice from the sidewalks that don’t involve salt use, options that can more easily be done on a smaller scale on their specific sections of sidewalk rather than on a larger scale, such as the entire street width. Additionally, providing safe transportation options that allow people to make short trips by not using a car is also an important aspect of our sustainability goals.
Assessments
Project Limits
2022: Lake Mendota Dr. from Baker Ave. to Epworth Ct., and Capital Ave. from Lake Mendota Dr. to the lake
2023: Lake Mendota Dr. from Spring Harbor to the City/Village limits
2024: Lake Mendota Dr. from Epworth Ct. to Spring Harbor, and Norman Way from Lake Mendota Dr. to the lake
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
- Feb. 24, 2022 Public Information Meeting Recording
- Feb. 24, 2022 Public Information Meeting PowerPoint Presentation
- Jan. 11, 2022 Public Information Meeting Recording
- Jan. 11, 2022 Public Information Meeting PowerPoint Presentation
Thank you to everyone who has given feedback and input so far on this project. We’re grateful for your comments, calls, suggestions and feedback. We also want to provide more opportunities to you to share your information in the process as the design moves forward. This includes additional public meetings, as well as presentations to the Transportation Commission, Board of Public Works, and the Common Council. The dates and times for all of these meetings will be updated on the project page. The Transportation Commission provided some initial input at the meeting on January 12, and their recommendation was to move forward with a preliminary design that includes sidewalks. We certainly welcome all feedback on the project, but major policy decisions, such as the installation of sidewalks, need to consider the City’s adopted plans and policies along with the recommendations of the City’s committees.
Survey
Lake Mendota Drive Electronic Survey No. 1 results
Lake Mendota Drive Survey No. 2 , open until March 9, 2022.
City Process, Meetings
Transportation Commission: 1/12/22 – as a key decision making body on these types of projects, initial input from the Commission was received at this meeting
Second Public Informational Meeting - late February or early March (date pending)
Transportation Commission: 3/9/22 (estimated date) - present base street design for LMD
Board of Public Works: 3/16/22 (estimated date) - present base street design for LMD
Board of Public Works: 4/20/22 (estimated date) - public hearing on 2022 project only
Common Council: 5/10/22 (estimated date) - public hearing on 2022 project only