Last Updated: 12/23/2022

Follow the Progress on Fire Station 14's Flickr Page


Updated: October 17, 2019

Status: Completed!

Here are a few features of the new FS14 Training Tower:

FS14TrainingTower1
FS14TrainingTower2

FS14TrainingTower3

 


Fire Station 14 Training Tower

The training tower located at Fire Station 14 is a stand-alone 800 square foot, tri-level treated wood structure. The building is an open air structure for training purposes and will not be occupied at non-training times. The building will not contain plumbing, HVAC, electrical or data systems.


City User Agency: Madison Fire Department

Planning and Design: 2019
Advertisement of Bid: 05/24/2019 available on Bid Express
Bid Due Date: 06/06/2019
Construction Start Date: 07/24/2019
Expected Completion Date: 10/11/2019

"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."


Rendering of Proposed Training Tower

FS14 Training Tower