Last Updated: 07/21/2022

Project Update

2022 Update:

This project is complete. 

Project Overview

This project is a road reconstruction that will include the replacement of sanitary sewer mains and laterals, storm sewer, road base and pavement, curbs, gutters, driveway aprons, and pedestrian ramps.  Sidewalk segments will be replaced as needed.  Construction is scheduled to start spring 2021, and will have a duration of approximately six months.  During construction, the roads within the project limits will remain closed to thru traffic and open to residents only.

Plan view

Project Limits

Dunning Street - Atwood Avenue to the railroad tracks

Jackson Street - St. Paul Avenue to the railroad tracks

Lafollette Avenue - Division Street to Ohio Avenue

Project Schedule

Start of Construction:  Spring of 2021
Bid Advertisement: Oct. 29, 2020
End of Construction:  Fall of 2021

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:

Public Information Meetings

A public information meeting for this project was held virtually Sept. 10, 2020. 

Sept. 10, 2020 Public Information Meeting PowerPoint Presentation
Sept. 10, 2020 Public Information Meeting Recorded Meeting

City Meetings, Process

Board of Public Works: Oct. 7, 2020

Common Council: Oct. 20, 2020, approved