Dean Ave., East and Allis Ave.

Last Updated: 11/10/2020

Latest Update

11/10/2020 Update:
Thank you everyone who attended the Nov. 9 Virtual Public Information Meeting.
You can now watch the Nov. 9, 2020 Public Information Meeting Recording.
Nov. 9 2020 Public Information Meeting PowerPoint Presentation
Property owners within the project limits have until Nov. 23, 2020 to complete the project survey.

Project Overview

In 2021, the City plans to reconstruction portions of E. Dean Ave., Allis Ave., Seth Cir. And Tyler Cir.  The proposed project would include replacement of the sanitary sewer and water mains, installation of new storm sewer, and replacement of the asphalt pavement with new curb and gutter and likely sidewalk.  There are a variety of options that may be possible for how the street is reconstructed, and these options will be discussed at future public informational meetings and City committee meetings.
Preliminary Plans Option No. 1

Project Limits

E. Dean Ave. from Monona Dr. to Allis Ave.
Allis Ave. from E. Dean Ave. to Turner Ave.
Seth Circle from Dean Ave. to the southerly end
Tyler Circle from Dean Ave. to the northerly end

Project Schedule

Anticipated bid date of February 2021, with construction during the spring/summer of 2021

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:

Public Information Meetings

Nov. 9, 2020 Public Information Meeting Recording

Nov. 9 2020 Public Information Meeting PowerPoint Presentation

City Meetings, Process

Anticipated schedule; dates are subject to change
Transportation Commission: Nov. 18, 2020
Board of Public Works: Dec. 16, 2020
Common Council: Jan. 5, 2021